Gonzaga University - start of gamelines
Gonzaga University - ready for logos and gamelines
2nd seal coat was applied this afternoon. Tomorrow we begin the gamelines and logos.
Gonzaga University - updated progress
We have completed the sanding of the new floor, the first seal coat has been applied with the second seal going down later today. On Wednesday June 10th we will start gamelines and logos. Our completion date is still on schedule for next Thursday June 18th.
Gonzaga University - sanding
We are currently sanding the floor. No new pictures this week until the GoPro video is released for it.
Gonzaga University - time lapse video of the subfloor install
Gonzaga University - time lapse video of the demo.
Gonzaga University - maple install day three
Gonzaga University - maple install day two
Gonzaga University - maple install day one
Gonzaga University - maple begins
Gonzaga University - subfloor complete
Gonzaga University - today's progress
Nicely done by the crew!
Gonzaga University - subfloor progress
Gonzaga University - beginning of subfloor install
Gonzaga University - versa shield install due to slab moisture
Gonzaga University - another view from the first day of demo
Additional photos to come soon.
Gonzaga University - is ready for the new floor
Demo is complete. Install begins on Monday May 18th.
Gonzaga University - maple and subfloor gone
Gonzaga University
On Monday May 11th we started the demo of the main gym at Gonzaga University. The GoPro is up and running! More pictures and video to come!